The designer estimates 8,000 to 9,000 man hours for this 42 footer
http://store.gartsideboats.com/collections/sailboats/products/12-9m-cutter-design-174
A first time builder working alone would almost certainly not be that efficient.
But here you go:
60 hours/week for 26 weeks ~1500 hours
Working 20 hours/ weekend the remaining 7,000 man hours would take 350 weekends or an additional 6.7 years.... assuming no days or weekends missed.
A comparable 50 foot boat would require many more man hours, not double but possibly nearly so.
IMO you far overestimate the value of your house and cabinetmaking experience. I'm not belittling those skills, they have value, but there will be places where they lead you quite a ways in the wrong direction as well.
Take a set of house plans home on Friday and study them over the weekend. On Monday you can start making lumber into house parts.
Take home a set of plans for a 50 footer and on Monday you may be ready to start building a loft floor and suitable long battens and transferring the lines and offsets to full size drawings. First time, alone ..... you'd be lucky to have it lofted in 2 weeks. You haven't made anything yet. BTW That 60 x 20 shed won't feel spacious at all with a 50 x 12' or 14' boat in it.
Your inexperience and house building background may lead you to take shortcuts in the lofting process. If so you will probably give back those man hours many times over in the months to come.
The proper way to go about this would be to have study plans in hand for a specific boat. Most designers charge nominal fee for study plans. Every detail changes the building time. I wrote a response to one of your posts a few days ago but you deleted the post while I was writing. If I can find it I'll post it below.
http://store.gartsideboats.com/collections/sailboats/products/12-9m-cutter-design-174
A first time builder working alone would almost certainly not be that efficient.
But here you go:
60 hours/week for 26 weeks ~1500 hours
Working 20 hours/ weekend the remaining 7,000 man hours would take 350 weekends or an additional 6.7 years.... assuming no days or weekends missed.
A comparable 50 foot boat would require many more man hours, not double but possibly nearly so.
IMO you far overestimate the value of your house and cabinetmaking experience. I'm not belittling those skills, they have value, but there will be places where they lead you quite a ways in the wrong direction as well.
Take a set of house plans home on Friday and study them over the weekend. On Monday you can start making lumber into house parts.
Take home a set of plans for a 50 footer and on Monday you may be ready to start building a loft floor and suitable long battens and transferring the lines and offsets to full size drawings. First time, alone ..... you'd be lucky to have it lofted in 2 weeks. You haven't made anything yet. BTW That 60 x 20 shed won't feel spacious at all with a 50 x 12' or 14' boat in it.
Your inexperience and house building background may lead you to take shortcuts in the lofting process. If so you will probably give back those man hours many times over in the months to come.
The proper way to go about this would be to have study plans in hand for a specific boat. Most designers charge nominal fee for study plans. Every detail changes the building time. I wrote a response to one of your posts a few days ago but you deleted the post while I was writing. If I can find it I'll post it below.