as a joiner I continuously make kitchens. some very complicated. I would be very disappointed if it took longer than 3 weeks to build a large one.
I'm having difficulty with the notion that fitting out the boat will take the bulk of the build time. Surely all the lockers and cupboards don't amount to a large kitchen! Every thing will be built in the adjoining workshop, sprayed in the spray booth and then fitted to the boat.
Am I being to simplistic.
Ok so there's electrics/plumbing/rigging etc. but I honestly am having difficulty with the timings being posted
Ha ha ha ha - I once thought as you do. How hard can it be, I said to myself, as I started on a *much* more modest 12m steel hull...
Tell me - when was the last time you built a kitchen when EVERY SINGLE PIECE of material that went into it was a different size & shape??? Same for every piece of cabin sole, lining, settee etc etc?
And tell me - just *how* are you going to get those large sub-assemblies into your boat? The only way you can is to leave the cabin top off until you finish the interior. Regardless, you're going to have to lift them some 3 to 4 metres up in the air and move them sideways to lower into place. Just how much headroom and how big a crane do you have? Will those assemblies lend themselves to being lifted/slung in such a fashion?
When you *didn't* have 100mm or more to run your wires and plumbing?
When *every single piece* of the plumbing needed to not just run downhill, but sometimes run uphill as well, be sealed off if necessary from water *ingress*?
When you have 5 or 6 different plumbing systems to deal with, and their pumps, sea cocks, vents etc etc (salt water, fresh water, grey water, black water, holding tanks, deck fills/vents with waterproof fittings, water tankage, diesel tankage - probably something else I've forgotten)?
I have built 3 houses in my life, including a 3 storey 54 square steel post & beam one. I am a tool tragic of the worst type - I have a complete metalworking machine shop and a lot of big powered woodworking tools as well (3 phase industrial stuff, not big box hardware store). I am telling you, from my personal experience, that I could build 3 entire houses including doing all the plumbing & wiring, in less time than it'd take me to build one 12m boat.
I'm not trying to stop you from doing this - I'm just trying to make you realise just what you're letting yourself in for. It can be done and it has been done, but it's one hell of a lot of work, and it won't be quick.
PDW