Quote:
Originally Posted by Manie B View Post
look around everywhere
very very seldom does a project like this finish on time
go for the cheapest
the costs escalate soooo much anyway that you will **** yourself at the end

be warned - the 2 years will EASY EASY become 3

This line of thought (which is the same as liki's line of thought) is my natural, default mode of thinking. Keeping wasteful costs, like real estate, as low as possible will give the project a better financial "runway." In fact, the difference between the types of buildings at the 2 year mark is that of my engines! It would be like getting free engines if I build in the fabric building!

The reason I'm asking here is to be sure that building in a tent isn't a mistake for some reason. Heating and air conditioning costs in the tent will be enormous, but not nearly as expensive as monthly rent.

Manie, I take your advice to heart. I will add that I also have some professional experience and understand the costs and length of the project. My 1-2 year estimate is for the *hull only*, neglecting rigging, deck hardware, interior joinery and house systems. This is 1-2 years for a painted hull to be launched, if land-based expenses get out of hand. Fit out and interior joinery will likely take place in the water. I'm full time on this project from now until it's done, with help along the way from my wife and hired labor here and there.

Cost? I think I also have that down. I know exactly what my materials cost, what my real estate costs, what the cost of launching is, what the cost of additional labor is, what the cost of heating or cooling my build location is, what the cost of making mistakes is, what the cost of every piece of interior joinery and systems is (I have many years experience in that area) and also have a 20% margin added to the entire total. I think I'll come out on cost and on time, but don't we all say that!! ha ha ha
Reply With Quote
  #17  
Old 05-13-2010, 05:47 AM
ecflyer ecflyer is offline
Junior Member
 
Join Date: Jan 2009
Rep: 72 Posts: 76
Location: Green Bay, Wisconsin
It looks to me that the tent sides slope inward too rapidly to enable the construction of a 25' wide hull. I believe it will take more than 2 years to complete the hull so I would opt for the fabric bldg. Also, it will be extemely difficult or inconvenient to complete the fit out in the water. Remember, there is a ton of epoxy work left after the basic hull is built. I thought I was 95% done with my epoxy work after my hull & deck were complete and 3 years & 55 gallons of epoxy later, I am still using the stuff and may need to order another 5 gals. How you going to install the drive shaft, rudder shaft and thru hulls while the boat is in the water? If your going to do this work on land, beter figure on 4 years time, not 2. So the fabric bldg wins hands down, just maybe not the one you are considering.

Have a Spiffy G'Day
Earl
Reply With Quote
  #18  
Old 05-13-2010, 07:51 AM
hoytedow's Avatar
hoytedow hoytedow is offline
Resistor
 
Join Date: Sep 2009
Rep: 1871 Posts: 3,355
Location: Norte de Cuba
Quote:
Originally Posted by ecflyer View Post
It looks to me that the tent sides slope inward too rapidly to enable the construction of a 25' wide hull. I believe it will take more than 2 years to complete the hull so I would opt for the fabric bldg. Also, it will be extemely difficult or inconvenient to complete the fit out in the water. Remember, there is a ton of epoxy work left after the basic hull is built. I thought I was 95% done with my epoxy work after my hull & deck were complete and 3 years & 55 gallons of epoxy later, I am still using the stuff and may need to order another 5 gals. How you going to install the drive shaft, rudder shaft and thru hulls while the boat is in the water? If your going to do this work on land, beter figure on 4 years time, not 2. So the fabric bldg wins hands down, just maybe not the one you are considering.

Have a Spiffy G'Day
Earl
I agree. Quonset would work if it were on a vertical wall. How wide would quonset tent be at deck height, assuming hull was up on alignment jig?
__________________
Hoyt
"Lightning is very selective and will not strike crap." Wynand N
"We Redistribute World's Wealth By Climate Policy" UN IPCC Official
Reply With Quote
  #19  
Old 05-13-2010, 09:57 AM
CatBuilder CatBuilder is offline
Senior Member
 
Join Date: Jul 2009
Rep: 1320 Posts: 3,040
Location: Northeast
Yup... you guys are right. I may have to alter the tent model. There are literally hundreds of combinations to choose from. I'll get one that fits. They're modular so you can make them as long as you want. As for width, they go up in size to stadiums and arenas, so I should be good there. I think the next jump up is 35' or 38' wide. They also have models with vertical walls.

Earl, do you think it will take more than 4000 man hours to complete just the hull? People I've talked to that have built these Kurt Hughes boats have suggested 4000 man hours was the time it took to build the entire 45' boat, fitted out, not just the hull. Thoughts?

You have to give me a little credit here, in general. I've been on the water since the 90's. I've actually lived at sea since the early 2000's, barely even stepping foot on land in that decade. I just came back on land to build this boat. I did marine repairs between charters all that time. My repair work consisted of interior/systems work on floating boats and a few patch jobs. I have a lack of experience with composite wood/epoxy, which is why I have some pretty basic questions here. I'm sure I'll remember to put the through hulls in before I launch! ha ha ha As for all that machinery you're describing that drags below the water slowing the sailboat down? I'm not putting any of that on! ha ha ha Outboards only, so I can sail in light winds too.

Also, I've refit, put systems in and modified many *many* interiors on the water, the majority done at anchor. It's not really any more difficult than doing it on land. Load the boat up with all the materials and tools, make sure your power system is up to the task and build away like you would on land.

Sorry... I don't mean to sound confrontational... your advice is very good. I've just got many years at sea under the belt and I've done this stuff so many times, I have my ways of doing it at anchor. I'm a guy who has moved ashore from boats for a couple years to build one. I'm not a land guy.
Reply With Quote
  #20  
Old 05-13-2010, 11:42 AM
hoytedow's Avatar
hoytedow hoytedow is offline
Resistor
 
Join Date: Sep 2009
Rep: 1871 Posts: 3,355
Location: Norte de Cuba
No one impugns your intellect. We are all learners here.
__________________
Hoyt
"Lightning is very selective and will not strike crap." Wynand N
"We Redistribute World's Wealth By Climate Policy" UN IPCC Official
Reply With Quote
  #21  
Old 05-13-2010, 12:47 PM
apex1
Guest
 
Posts: n/a
Quote:
Originally Posted by CatBuilder View Post
Earl, do you think it will take more than 4000 man hours to complete just the hull? People I've talked to that have built these Kurt Hughes boats have suggested 4000 man hours was the time it took to build the entire 45' boat, fitted out, not just the hull. Thoughts?
Never it takes 4000 hrs to build these hulls!

But I doubt this figure for the entire boat as well! Except that is a next to no standard, cheap, interior and outfitting.

Have no idea about these boats as I mentioned on one of your other fivethousand threads, but when you calculate a decent 1 kilogram of boat per manhour, you will be on the safe side! (taking your described experience into account)

Regards
Richard
Reply With Quote
  #22  
Old 05-13-2010, 01:54 PM
ecflyer ecflyer is offline
Junior Member
 
Join Date: Jan 2009
Rep: 72 Posts: 76
Location: Green Bay, Wisconsin
I never built a cat type boat so I can't answer your man hours question directly. I can only speak from the experience of building my own 47' ketch, cold molded wood, monohull. It took me 9 months (approx 1200 hrs) for the hull. Then another 2000 hrs for bulkheads, deck and interior floors and in the process became senitized to epoxy. Then another 2000 hrs to drop the engine in, drive shaft, skeg & rudder shaft, tankage and battery boxes. At the total of 5200 hrs point, I was finally in position to install the thru hulls and deck fills Plumbing needs to be somewhat done for this). I anticipate total construction time to be 6500 hrs.

Have a Spiffy G'Day
Earl
Reply With Quote
  #23  
Old 05-15-2010, 09:32 AM
CatBuilder CatBuilder is offline
Senior Member
 
Join Date: Jul 2009
Rep: 1320 Posts: 3,040
Location: Northeast
Quote:
Originally Posted by apex1 View Post
Never it takes 4000 hrs to build these hulls!

But I doubt this figure for the entire boat as well! Except that is a next to no standard, cheap, interior and outfitting.

Have no idea about these boats as I mentioned on one of your other fivethousand threads, but when you calculate a decent 1 kilogram of boat per manhour, you will be on the safe side! (taking your described experience into account)

Regards
Richard
That is a good rule of thumb figure. I've never been able to really get an accurate build time from anyone. Thank you. Using your formula and the boat's weight, in kilograms, I have the following:

http://www.multihulldesigns.com/desi...k/45bdcat.html

Boat weighs 5,398kg. This means roughly 5,398 man hours of work to complete. My allocation of 2000-4000 hours for the hulls sounds about right if the total boat would take 5,398 hours, correct?

I will indeed be taking some "short cuts" in the final fit out. Although she's a charter boat, I'm not going to go crazy with intricate interiors. Things will be kept simple and with a minimalist style. Beauty for charter will come from decorative things like seat cushions and such. The boat will not have highly intricate joinery, but rather tasteful, but utilitarian joinery. I will let the accents (flatware, dishes, table coverings, etc...) carry the boat for marketability.

I like this rule of thumb though. It helps to picture the amount of time this project will take. Thank you for this information.
Reply With Quote
  #24  
Old 05-15-2010, 09:36 AM
CatBuilder CatBuilder is offline
Senior Member
 
Join Date: Jul 2009
Rep: 1320 Posts: 3,040
Location: Northeast
Quote:
Originally Posted by ecflyer View Post
I never built a cat type boat so I can't answer your man hours question directly. I can only speak from the experience of building my own 47' ketch, cold molded wood, monohull. It took me 9 months (approx 1200 hrs) for the hull. Then another 2000 hrs for bulkheads, deck and interior floors and in the process became senitized to epoxy. Then another 2000 hrs to drop the engine in, drive shaft, skeg & rudder shaft, tankage and battery boxes. At the total of 5200 hrs point, I was finally in position to install the thru hulls and deck fills Plumbing needs to be somewhat done for this). I anticipate total construction time to be 6500 hrs.

Have a Spiffy G'Day
Earl
Excellent input, Earl. Thank you for the house figures.

It does surprise me that the 47' hull was complete in only 1200 hours, especially for a cold molded hull. I'm impressed!

That's a shame you became sensitized to epoxy. What are you doing now to keep you from being exposed? How are you working so you are not exposed to epoxy? Was it a skin sensitization or are you having problems with fumes?
Reply With Quote
  #25  
Old 05-15-2010, 12:51 PM
apex1
Guest
 
Posts: n/a
Quote:
Originally Posted by CatBuilder View Post
Boat weighs 5,398kg. This means roughly 5,398 man hours of work to complete. My allocation of 2000-4000 hours for the hulls sounds about right if the total boat would take 5,398 hours, correct?
You´re welcome.

No, it will take much less than 2000 hrs for the hulls. Although I have no experience in this building method, I can clearly see that it is far less of a job than cold moulded for example. Should be equal to strip planking in overall time consumption, therefore closer to 1000 or 1500 hrs. (again, it all depends of course. When your cabinetry is part of the srtucture, therefore part of the hull building process, well, you know)

Commercially built, the hull is about 15% of the cost and effort (in wood epoxy),
for a homebuilt about 20 to 25%. Many homebuilders have it easier with the smaller items, and / or cut the corners on them.

Regards
Richard
Reply With Quote
  #26  
Old 05-17-2010, 06:01 PM
ecflyer ecflyer is offline
Junior Member
 
Join Date: Jan 2009
Rep: 72 Posts: 76
Location: Green Bay, Wisconsin
Catbuilder,
After becoming senatized to epoxy, I had to wear a full suit for protection. My whole body broke out in as rash of pimples just like poison ivy/oak and the itch was unbearable. If I get any sanding dust on my hands, I quickly wash it off thourghly. There are no fumes with epoxy so that is never an issue. The mistake I made was in wearing regular blue jeans while working with epoxy. Some would drip on my shirt and pants w/o my notice. This skin contact eventually builds up and finally one becomes sensitized. I finished my boat but was extremely careful after that. I wore a water proof rain suit while gluing. I applied at least 100 gallons of epoxy after becoming sensitized, so it's not the end of the world.
Have a Spiffy G'Day
Earl
Reply With Quote
  #27  
Old 05-20-2010, 01:41 AM
Submarine Tom's Avatar
Submarine Tom Submarine Tom is offline
Mariner
 
Join Date: Aug 2008
Rep: 937 Posts: 1,941
Location: North America (not USA and not Mexico but, below the 49th parallel, and on the Pacific coast)
Tent it is then.
Reply With Quote
Reply



Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
boatbuilding/warehouse job JR-Shine Services & Employment 0 02-12-2007 11:37 AM
Newbie to boat design and building wants to make own boat bigisland Boat Design 2 01-20-2007 12:03 AM
boat building UK Jurach Education 0 03-24-2006 01:24 PM
PT Boat building/warehouse man needed JR-Shine Services & Employment 0 12-19-2005 03:07 PM
Help!!! Building a new Boat!!!! Hannibal221 Wooden Boat Building and Restoration 6 06-23-2005 09:31 AM


All times are GMT -5. The time now is 10:26 AM.


Powered by: vBulletin Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.
Web Site Design and Content Copyright ©1999 - 2012 Boat Design Net